Projects

Marsa Junction Project

Client

Infrastructure Malta

Project Background

The Marsa Junction Project included the development of a new multi-level intersection to replace the Addolorata traffic lights system.

The project included 12 kilometres of new uninterrupted lanes, grade-separated at three levels. This resulted in creating direct northbound and southbound connections between Triq Aldo Moro, Vjal Sir Paul Boffa, Vjal Santa Lucija, Triq Giuseppe Garibaldi and Triq il-Marsa (to Qormi).

marsa junction project construction monitoring

Request​

AIS Environment carried out the Environmental Monitoring for the Project. This consisted of an analysis on air quality and ecology, noise monitoring, tree permits and archaeological monitoring.

Our Input:

Environmental Monitoring

Focused on general construction site practices, air quality, ecology and noise monitoring.

Regular site inspections

A monitor walked through the entire site and took note of any cases of non-compliance for which remedial action needed to be taken

Key role monitoring different processes

Pruning, transplanting, planting and uprooting of trees as authorised and permitted by the competent authorities.

Discover the assessments performed on the Malta-Sicily Gas Pipeline